Hi, I am using workbench 3.0.2 to run VMware Esxi 5.5 U2 NIC certification.
When I test the VLAN cases, i.e, HwVLANRxTx and VLANGuestTagging, the test will enter a dead loop, and below are the logs:
Mar 27 2015 00:46:53 : WLMANAGER ] [0] FRAMEWORK: Workload NetPerfTst is still Running
[Mar 27 2015 00:46:54 : STAFBASE ] [1] FRAMEWORK: RC:37
[Mar 27 2015 00:46:54 : WLBASE ] [1] DEBUG: The Duration for NetPerfTst is 180
[Mar 27 2015 00:46:54 : WLBASE ] [1] DEBUG: Remaining time for NetPerfTst is -51354
[Mar 27 2015 00:46:54 : WLMANAGER ] [1] DEBUG: NetPerfTst is stopped
[Mar 27 2015 00:46:54 : STAFBASE ] [1] FRAMEWORK: Executing STAF command: staf 192.168.49.182 PING PING
[Mar 27 2015 00:46:54 : STAFBASE ] [1] FRAMEWORK: Executing STAF command: staf local queue get wait 1000
[Mar 27 2015 00:46:55 : STAFBASE ] [1] FRAMEWORK: RC:37
[Mar 27 2015 00:46:55 : WLBASE ] [1] DEBUG: The Duration for NetPerfTst is 180
[Mar 27 2015 00:46:55 : WLBASE ] [1] DEBUG: Remaining time for NetPerfTst is -51355
[Mar 27 2015 00:46:55 : WLMANAGER ] [1] DEBUG: NetPerfTst is stopped
[Mar 27 2015 00:46:55 : STAFBASE ] [1] FRAMEWORK: Executing STAF command: staf 192.168.49.182 PING PING
[Mar 27 2015 00:46:55 : STAFBASE ] [1] FRAMEWORK: Executing STAF command: staf local queue get wait 1000
[Mar 27 2015 00:46:55 : WLMANAGER ] [0] FRAMEWORK: Workloads Running are : PingTst NetPerfTst
Note that the duration is 180s and it should stop when remaining time is 0, but it continues and the remaining time keep decreasing even it is negative.
And I don't see any traffic on test NIC when this happens.